Status of Ongoing/Pending Railway Projects in Uttar Pradesh (2012-2013-upto October 2012) | |||||
(Rs. in Crore) | |||||
Projects | Latest Anticipated Cost | Outlay 2012-13 | Expenditure upto Oct. 2012 | Physical Progress | Target date of Completion |
New Line | |||||
Agra-Etawah (114Km) | |||||
Deoband-Roorkee (27km) | |||||
Etawah-Mainpuri (57.5km) | |||||
Guna-Etawah (345km) | |||||
Chhitauni-Tumkuhi Road (62.50km) | |||||
Hathua-Bhatni (80km) | |||||
Rampur-Lalkuan-kathgadam | |||||
Lalitpur-Satna, Rewa-Singrauli & Mahoba-Khajraho (541km) | |||||
Unchahar-Amethi (66km) | |||||
Doubling | |||||
Aunrihar-Manduadin (39km) | |||||
Bhimsen-Jhansi (206km) | |||||
Chhapra-Ballia (65km) | |||||
Palwal-Bhuteswar (81km) | |||||
Utretia-Rai Bareli (66km) | |||||
Meerut-Muzaffar Nagar (55.47km) | |||||
Balance 148km of Utretia-Zafrabad Section | |||||
Barabanki-Burhwal (29km) | |||||
Ghaghara Ghat-Chowka Ghat (5.6km) | |||||
Gorakhpur-Baitalpur (38km) | |||||
Tundla-yamuna Bridge (21km) | |||||
Lohta-Bhadol (39km) | |||||
Phahamau-Allahabad (13km) | |||||
Bhadai-Janghai (31km) | |||||
Gauge Conversion | |||||
Kaptanganj-Thawe-Chhapra (233km) | |||||
Gonda-Gorakhpur (260km) | |||||
Gonda-Bahraich (60km) | |||||
Bhojipura-Tanakpur (102km) | |||||
Kanpur-Kasganj-Mathura (545km) | |||||
Lucknow-Pilibhit (263km) |