Sample Data Format
 Length and Cost of Ongoing National Highway Projects in Odisha
(As on 13.06.2014 to 03.03.2024) 
 Projects  Length in Km.  Sanction Cost
(Rs. in Crore) 
 Appointed
Date 
 Schedule
Completion
Date 
 Target
Date of
Completion 
 4-Laning of Angul- Sambalpur Section of NH-42 (EPC)           
 4-Laning of Teleibani – Sambalpur Section of NH-6 (EPC)           
 4-Laning of Cuttack –Angul Section of NH-42 (EPC), Package – I           
 4-Laning of Cuttack –Angul Section of NH-42 (EPC), Pacakage– II           
 4-Laning of Rimuli-Koida Section of NH-215 (New NH 520 (EPC)           
 4-Laning of Koida – Rajamunda Section of NH-215 (New NH 520) (EPC)           
 4-Laning of Biramitrapur- Brahmani Bridge end Section of NH-23 (EPC)           
 6-Laning of Chandikhole- Bhadrak Section of NH-5 (New NH 16) (HAM)           
 6-Laning of Puintola to Tangi Section of NH-5 (New NH 16) (EPC)           
 4-Laning of Rajamunda to Barkote Section of NH-23 (EPC)           
 4-Laning of Brahmani bridge end to Rajamunda Section of NH-23 (EPC)           
 4-Laning of Talcher – Kamakhyanagar Section of NH-200/23 (New NH 53) (EPC)           
 6-Laning of Tangi- Bhubaneswar Section of NH-5 (New NH 16) (EPC)           
 6-Laning of Bhadrak- Balasore Section of NH-5 (New NH 16) (HAM)           
 4-Laning of Duburi Chandikhole Section of NH-200           
 3-VUPs at Balikuda, Sikharpur & Badachana in Bhubaneswar-Chandikhole Section of NH-16           
 Flyover at Hanspal of Chandikhole-Jagatpur- Bhubaneswar Section of NH-5           
 Construction of VUPs at Km.11.330 (Kalabadia Chowk) and at Km.14.280 (Kuliana Village) in
Balasore-Baripada- Jharpokharia Section of NH-5 
          
 Balance work of 4-Laning of Panikoili-Rimuli Section of NH-20           
 6L Major Bridge including Approaches from Km.172.895 to Km. 173.670 of NH-520           
 6L of Dhanara - Hatibena Section from Km 124.611 to km 146.50 of NH-130- CD (Package – OD-1)           
 Widening and Strengthening to 2L+PS from km 162/700 to km 192/450 (Amalabata to
Tandikana) of NH-326 
          
 Widening to 2L+PS from km 0/00 to km 81/00 & km 93/00 to km 119/00 (Charichhak to
Bhanjanagar) of NH-157 
          
 Widening to 2L+PS from km 50/0 to km 140/9 (Sonepur to Madhapur) of NH-57           
 Widening to 2L+PS from km 239/900 to 294/300 (Nayagarh to Khurda) of NH-57           
 Widening & Strengthening to 2L+PS from km 58/000 to 116/100 (Naktideul to Boudh) of NH 153-B           
 Widening to 2L+PS from Km 0/000 to 41/055 (Chandili- Borigumma) of NH 63           
 Widening to 2L+PS from Km 173/370 to 229/400 (Baliguda to Daringbadi) of NH-59           
 Widening to 2L+PS from Km 269/300 to 328/200 (Jharsuguda to Bhojpur) of NH-49           
 Widening to 2L+PS from km 319/280 to 345/480 (Boriguma - Jeypore) of NH-26           
 Widening to 2L+PS from km 0/000 to 35/840 (Tiring to Rairangpur Section) of NH-220           
 Widening to 2L+PS from km 195/600 to 218/050 (Odisha-Chhatishgarh Border to
Baldhiamal Chhak) of NH-130C 
          
 Widening to 2L+PS from Km 294/280 to 319/280 (Nabarangpur to Borigumma) of NH-26           
 Widening to 2L+PS from km 296/500 to 336/500 (Mundamarai to Ratanpur Section) of NH-59           
 Construction of Road from km 0/0 to 72/0 of NH-26 such as 4 lane from km 0/0 to 21/0
(Bargarh to Barpali) and 2L+PS from km 21/0 to72/0 (Barpali to Bolangir) 
          
 Strengthening to NH-26 from km 351/480 to 367/480 & from km 376/480 to 434/767
(Koraput to Sunki Ghat) 
          
 Strengthening to NH-326A from km 70/0 to km 102/90           
 Strengthening to NH-326 from km 311/700 to 327/700           
 Strengthening to NH-20 from km 0/0 to 14/0 (Champua-Rimuli) & Link Road to NH-20
from 14/0 to 14/69 (at Parsala) and Connecting road from Rimuli Square at km 14/0
to 1/430 of NH-520 
          
 Strengthening to NH-326 from km 413/700 to km 429/700           
 Strengthening to NH-326A from km 0/0 to 35/0 in the State of Odisha on EPC Basis.           
 Strengthening of Road from Km 174/570 to 186/094 Km, 210/570 to 234/751 & Km 235/
748 to 243/648 km of NH-20” in the State of Odisha on EPC basis 
          
 Strengthening of Existing Carriageway from km 277/461 to 280/249 Km, 281/
400 to 286/725 Km, 287/883 Km to 289/454km, 304/720 km to 341/741 km & Km 346/
000 to 360/391 km of NH-55” in the State of Odisha on EPC basis 
          
 Construction of Truck Parking at Bijakhaman of Bolangir Town from km 79/700 to
80/00 Adjacent to NH-26 in the State of Odisha. 
          
 Removal of Black Spot "Haladia Chhaka Areda" of NH-316 from km 12/900 to
13/400 and Black Spot "Nuanai Chhak" by Improving Road Safety through
Improvement of Junction and Implementing Permanent Measures etc. 
          
 Reconstruction of Proposed High Level Bridge over Pochaka Nallah at km
17/950 of NH-326 (Single Span of 18.00 m RCC T- Beam & Slab Bridge with Footpath)
in the State of Odisha. 
          
 Rehabilitation of Tel Bridge between 126/690 to 127/163 of NH-26 such as Providing
Mastic Asphalt, BC, Crash Barriers for the year 2019-20 in the State of Odisha 
          
 Re-construction of HL Bridge over Kantyali Nallah at 47/200 km of NH-153B for
the year 2020-21 in the State of Odisha. 
          
 Rehabilitation and Upgrading to 2 Lanes/2 Lane with Paved Shoulder from Km 90/0
to 158/0 (Nuapada to Bangomunda) of NH-217 under Phase-I of NHIIP. 
          
 India           
 
 
A storehouse of socio-economic statistical of 620 districts. A cluster of 11 associate websites
Provides election data for all 543 parliamentary and 4120 state assembly constituencies
A collection of over 4000 data-oriented publication in print, eBook, eFlipbook & web-based access formats
A comprehensive collection of Infographics, videos, maps and charts on various socio-economic and electoral Insights
An e-resource providing socio-economic statistical information about India, its states, sectors, regions, and districts.
A one-stop-app for all who are craving for the latest economic facts and figures of India.
One-of-a-kind online learning platform offering specialised courses and also providing interactive learning.
Twenty Four years of serving socio-economic and electoral research fraternity in india and abroad.
© Datanet India Pvt. Ltd.