Status of Ongoing/Pending Railway Projects under Northern Railways in India (2012-2013 and 2013-2014) | |||||
(Rs. in Crore) | |||||
Project | Latest Anticipated Cost | Anticipated Expenditure 2013 | Proposed Outlay 2013-14 | Physical Progress | Remarks/Target Date of Completion |
New Lines | |||||
Nangal Dam-Talwara (83.74 km) | |||||
Chandigarh-Ludhiana (112 km) | |||||
Jind- Sonepat (89 km) | |||||
Chandigarh-Baddi (33.23 km) | |||||
Deoband-Roorkee (27.45 km) | |||||
Bhanupalli-Bilaspur-Beri(63.1 km) | |||||
Qadian-Beas (40 km) | |||||
Unchahar-Amethi (66 km) | |||||
Rohtak- Meham-Hansi (68.8 km) | |||||
Rishikesh-Karanprayag (125 km) | |||||
Udhampur-Srinagar-Baramula Rail Link Project | |||||
Doublings | |||||
Jallandhar-Jammu Tawi (203 km) | |||||
Dayabasti Grade Separator | |||||
Utretia-Zafrabad (Balance 148 km) | |||||
Tughalakabad-Palwal 4th Line | |||||
Phaphamau-Allahabad (13 km) | |||||
Mansa-Bhatinda (53 km) | |||||
Lahota- Bhadoi (39 km) | |||||
Ambala Cantt.-Dhappar (23 km) | |||||
Chakki Bank Bharoli (3.5 km) | |||||
Jallandhar Cantt.-Suchipind (3.5 km) | |||||
Sambha-Vijaypur Jammu | |||||
Bhadoi-Janghai (31 km) | |||||
Kathua-Madhopur Pb. Doubling Across Ravi Bridge | |||||
Kathua-Madhopur Pb. Doubling Across BR. No. 16,18 & 19. | |||||
Mirthal- Bhangala | |||||
Anand Vihar-Tilak Bridge 3rd and 4th line (9.77 km) | |||||
Meerut-Muzaffar Nagr (56 km) | |||||
Haridwar- Laksar (27 km) | |||||
New Delhi- Tilak Bridge 5th & 6th Line Doubling (2.65 km) | |||||
Utretia-Rae Bareli Doubling (65.6 km) |