State-wise Status of Ongoing Infrastructure Projects in North-Eastern Region of India (As on 01.05.2010) | |||||||
(Cost : Rs. in Crore) | |||||||
Project Name | DOA | DOC Original | DOC Anticipated | Cost Original | Cost Anticipated | Cost Overrun (%) | Time Overrun in Months |
Assam | |||||||
Assam Renewal Project For Group A | |||||||
Assam Telecom Circle, Phase-V.I, 2G and 3G | |||||||
Bijni To Assam /Wb.Border (Nh-31.C)(2)(Nhai) | |||||||
Bijni To Assam Wb Border (Nh-31.C)(1)(Nhai) | |||||||
Bijni To Assam/Wb Border Ph.Ii, Km.30.00 To 0.00, Nh-31 C | |||||||
Bongaigaon Thermal Power Project | |||||||
Brahamaputra Bridge At Bogibil and Link Lines,Nefr | |||||||
Brahmputra Bridge,Nh No-31 | |||||||
Dakoba To Nagaon (Nh-36)(Nhai) | |||||||
Dharamtul To Sonapur (As-19) | |||||||
Dharamtul To Sonapur,Km 205-183 (As-20) | |||||||
Guwahati To Nalbari (As-5) | |||||||
Guwhati To Nalbari (As-4) | |||||||
Harangajo To Maibang (As-23), Km.126.450 To Km.140.700 | |||||||
Harangajo To Maibang, Nh-54 | |||||||
Harangajo To Maibang,Km 164.08-190.587 Nh-54 | |||||||
Ior Geleki (Ongcl) | |||||||
Ior Lakwa - Lakhmani (Ongcl) | |||||||
Ior, Rudrasagar (Ongcl) | |||||||
Lanka To Daboka (Nh-54)(Nhai) | |||||||
Maibang To Lunding (As-24), Km.111.000 To Km.126.450 | |||||||
Maibang To Lunding (As-25), Km.83.400 To Km.111.000 | |||||||
Maibang To Lunding (As-26), Km.60.500 To Km.83.400, Nh-54 | |||||||
Maibang To Lunding (As-27), Km.40.000 To Km.60.500 | |||||||
Msq Improvment Project | |||||||
Msq Upgradation Project At Digboi Refinery | |||||||
Msq Upgradation Project At Guwahati Refinery | |||||||
Nagaon Bypass (Nh-37)(Nhai) | |||||||
Nagaon To Dharamtul (As-2) | |||||||
Nalbari T Bijni (As-7) | |||||||
Nalbari To Bijni (As-6) | |||||||
Nalbari To Bijni (As-8) | |||||||
New B.G. Line From Azara To Byrnihat (Natinal Project) | |||||||
Pagladiya Dam Project | |||||||
Restoration With Gauge Conversion of Silighat Town | |||||||
Silchar-Udarband (Ph.Ii) Hn-54, Km.309 To Km.275 | |||||||
Sonapur To Guwahti (As-3) | |||||||
Total | |||||||
Arunachal Pradesh | |||||||
Construction of New Line from Harmati-Itanagar/Narhariagun | |||||||
Kameng Hydroelectric Project (Neepco) | |||||||
Lower Subansiri H.E.P (NHPC) | |||||||
Total | |||||||
Manipur | |||||||
Loktak D/S Hep (Nhpc) | |||||||
Total | |||||||
Meghalaya | |||||||
North East Indira Gandhi Institute of Health and Ms | |||||||
Total | |||||||
Mizoram | |||||||
Bhairabi Sairong | |||||||
Tuirial He Project (Neepco) | |||||||
Total | |||||||
Sikkim | |||||||
C/O New Airport-Sh: E/W In Cutting and Filling Geogrid Reinforced Retuning Wall At Pakyong (Sikkim) A | |||||||
Sevok Rangpo | |||||||
Total | |||||||
Tirpura | |||||||
Agartala Sabroom | |||||||
Tripura Gas Based Power Project | |||||||
Up-Gradation of Konaban Ggs and Pipeline Grid Project, Tripura | |||||||
Total |