Selected State-wise Status of Ongoing Hydro Power Projects (Running Behind Schedule)* in India (As on 01.02.2011) | |||||
Project Capacity/Agency/State Date of Approval | Commissioning Schedule | Delays Relating to Latest V/s Last Approved/ Original | Reasons for Time and Cost over Run | ||
Original MM/YY | Latest Approved MM/YY | Latest MM/YY | |||
Parbati II (4x200 MW) NHPC H.P 11.9.2002 | Sep. 09 (2009-10) | Sept.-14 (2014-15) | 5 year | Slow progress of HRT by TBM. Contractual issues. Ban on operation of stone crusher by Hon ble High Court of Himachal Pradesh. Delay in revised forest clearance. Delay in widening the project roads by HP, PWD. Slide in Power House area in Feb 07. Heavy | |
Chamera-III (3x77 MW) NHPC HP 01.09.2005 | Aug.-10 (2010-11) | Aug.-11 (2010-12) | 12 months | Murder of 3 persons and damage to equipments in June 2006. Washing away of Coffer dam during flash flood in July 2007. Shut down of main crusher plant by state govt. Shooting stone in right bank of Dam | |
Parbati-III (4x130 MW) NHPC HP 09.11.2005 | Nov-10 (2010-11) | March.-12 (2011-12) | 1 Year 4 Month | Poor geology in HRT, Delay in completion of E& M works. | |
Kol Dam (4x200 MW) NTPC H.P. 28.10.2002 | Apr-09 (2008-10) | Mar-13 (2012-14) | 3 Years 11 Months | Slow progress of lay/earth filling of dam, Grouting of dam alleries, Concreting of Spillway, Contractual issues, Delay in procurement of steel. | |
Rampur (4x68.67 MW) SJVNL HP 25.01.2007 | Jan-12 2011-12 | Sept-13 2013-14 | 1 Year 8 Months | Poor geology in HRT, Slope failure in Power House Area. | |
Uri-II (4x60 MW) NHPC J&K 01.09.2005 | Nov-09 (2009-10) | Nov-11 (2010-12) | 2 Year | Lack of resources with contractor. Slope failure in Dam area on 19.01.2008. Widening of NH 1A by BRO. Breaching of Coffer Dam on 19.05.10. Disturbance in Kashmir Valley since June, 2010. | |
Koteshwar (4x100 MW) THDC Uttarakhand 10.4.2000 | |||||
Loharinag Pala (4x150 MW) NTPC Uttaranchal 26.06.2006 | |||||
TapovanVishnughad (4x130 MW) NTPC Uttaranchal 11/2006 | |||||
Teesta Low Dam-III (4x33 MW) NHPC West Bengal 30.10.2003 | |||||
Teesta Low Dam-IV (4x40 MW) NHPC WB 30.09.2005 | |||||
Subansiri Lower (8x250 MW) NHPC Ar. Pradesh/Assam 09.09.2003 | |||||
Chutak (4x11 MW) NHPC J&K 24.08.2006 | |||||
NimooBazgo (3x15 MW) NHPC J&K 24.08.2006 | |||||
Kameng (4x150 MW) NEEPCO Ar. Pd 02.12.2004 | |||||
Pare (2x55MW) NEEPCO Ar. Pradesh 04.12.2008 | |||||
State Sector | |||||
Northern Region | |||||
SawraKuddu (3x37MW) HPPCL, HP 10.11.04 | |||||
Uhl-III (3x33.33MW) BVPC 19.9.02 | |||||
Southern Region | |||||
Andra Pradesh | |||||
Priyadarshni Jurala (6x39.1MW) APGENCO, AP 24.07.2002 | |||||
Lower Jurala (6x40 MW) Andhra Radesh APGENCO 2007 | |||||
Karnataka | |||||
Nagarjuna Sagar Tail Pool Dam (2x25 MW) APGENCO 17.01.2005 | |||||
Kerala | |||||
Pallivasal 2x30MW KESEB 31.01.2007 | |||||
Tamil Nadu | |||||
BhavaniKattalai H.E. Project Barrage II (2x15 MW) TNEB 11.06.99 | |||||
BhavaniKattalai H.E. Project Barrage III (2x15 MW) TNEB 27.03.02 | |||||
North-Eastern Region | |||||
Meghalaya | |||||
Myntdu (2x42MW + (1x42 MW) MeSEB 09.06.2003 | |||||
Private | |||||
KarchamWangtoo (4x250 MW) H.P. M/s. JaypeeKarcham Hydro Corp Ltd.,(JKHCL) 31.3.03 (TEC) | |||||
Budhil (2x35MW) H.P. M/s. Lanco Green Power Pvt. Ltd. NA 02.06.06 | |||||
Malana-II (2x50MW) H.P. M/s. Everest Power Pvt. Ltd. 15.10.2004 (State Govt) | |||||
Srinagar (4x82.5 MW) Uttaranchal M/s Alaknanda Hydro Power Co. Ltd. 14.6.2000 (TEC) | |||||
Maheshwar (10x40 MW) SMHPC M.P. 30.12.96 | |||||
Teesta Stage III (6X200 MW) Sikkim M/s TeestaUrja Limited 12.05.2006 (TEC) | |||||
Teesta Stage VI (4X125 MW) Sikkim M/s Lanco Energy Private Limited 27.12. 2006 (TEC) | |||||
Rangit-IV HE Project (3X40 MW) JPCL 09.12.2005 | |||||
Chujachen (2x49.5 MW) Sikkim M/s. Gati Infrastructure Ltd. 30.11.04 |