Selected State/Project-wise Capacity of Hydro Electric Projects (Above 25 MW) under Execution in India (As on 17.07.2014) | ||||
States/Projects | Unit No. | Sector/Implementing Agency | Capacity (MW) | Likely Commissioning |
Jammu and Kashmir | ||||
Kishanganga 3x110= 330 MW | ||||
Baglihar-II 3x150= 450 MW | ||||
Ratle 4x205+1x30= 850 MW | ||||
Sub-total | ||||
Himachal Pradesh | ||||
Parbati St. II 4x200= 800 MW | ||||
Kol Dam 4x200= 800 MW | ||||
Rampur 6x68.67= 412 MW | ||||
Uhl-III 3x33.33= 100 MW | ||||
Kashang-I 1x65 =65 MW | ||||
Kashang-II & III 1x65 + 1x65= 130 MW | ||||
Sainj 2X50=100 MW | ||||
Swara Kuddu 3x37= 111 MW | ||||
Shongtong Karcham 3x150= 450 MW | ||||
Sorang 2x50= 100 MW | ||||
Tangnu Romai- I 2x22= 44 MW | ||||
Bajoli Holi 3x60= 180 MW | ||||
Chanju-I 3x12= 36 MW | ||||
Tidong-I 2x50= 100 MW | ||||
Sub-total | ||||
Uttarakhand | ||||
Tapovan Vishnugad 4x130=520 MW | ||||
Tehri PSS 4x250= 1000 MW | ||||
Lata Tapovan 3x57= 171 MW | ||||
Vishnugad Pipalkoti 4x111= 444 MW | ||||
Shrinagar 4x82.5= 330 MW | ||||
Phata Byung 76 MW | ||||
Singoli Bhatwari 3x33= 99 MW | ||||
Sub-total | ||||
Punjab | ||||
Shahpurkandi 3x33+3x33+1x8= 206 MW | ||||
Sub-total | ||||
Madhya Pradesh | ||||
Maheshwar 10x40= 400 MW | ||||
Sub-total | ||||
Maharashtra | ||||
Koyna Left Bank PSS 2x40= 80 MW | ||||
Sub-total | ||||
Andhra Pradesh/Telangana | ||||
Nagarujana Sagar TR 2x25= 50 MW | ||||
Lower Jurala 6x40= 240 MW | ||||
Pulichintala 4x30= 120 MW | ||||
Sub-total | ||||
Kerala | ||||
Pallivasal 2x30= 60 MW | ||||
Thottiyar 1x30 + 1x10= 40 MW | ||||
Sub-total | ||||
West Bengal | ||||
Teesta Low Dam-IV 4x40= 160 MW | ||||
Sub-total | ||||
Sikkim | ||||
Teesta- III 6x200= 1200 MW | ||||
Teesta- VI 4x125= 500 MW | ||||
Rangit-IV 3x40= 120 MW | ||||
Jorethang Loop 2x48= 96 MW | ||||
Bhasmey 3x17= 51 MW | ||||
Tashiding 2x48.5= 97 MW | ||||
Dikchu 3x32= 96 MW | ||||
Rangit-II 2x33= 66 MW | ||||
Rongnichu 2x48= 96 MW | ||||
Panan 4x75= 300 MW | ||||
Sub-total | ||||
Arunachal Pradesh | ||||
Subansiri Lower 8x250= 2000 MW | ||||
Kameng 4x150= 600 MW | ||||
Pare 2x55= 110 MW | ||||
Sub-total | ||||
Mizoram | ||||
Tuirial 2x30= 60 MW | ||||
Sub-total | ||||
Meghalaya | ||||
New Umtru 2x20= 40 MW | ||||
Sub-total | ||||
India |