Railway Zone-wise Outlay and Expenditure for Ongoing Doubling Projects in India (2014-2015) | |||
(Rs. in Crore) | |||
Project | Cost | Expenditure (As on 31.03.2014) | Outlay 2014-15 |
Central Railway | |||
Bhusawal-Jalgaon 3rd line (24 km) | |||
Godhani-Kalumna Chord (14 Km) | |||
Kalyan-Kasara - 3rd line (68 km) | |||
Panvel-Pen (35 Km) | |||
Panvel-Roha Land Acquisition (75 Km) | |||
Pen-Roha (40 Km) | |||
Wardha (Sewagram)-Nagpur 3rd line (76 km) | |||
East Coast Railway | |||
Banspani-Daitari-Tomka-Jakhapura (180 km) | |||
Bhadrak-Nergundi 3rd line (80 km) | |||
Brundamal-Jharsuguda-Flyover Connection for Joining DN Line (7 Km | |||
Cuttack-Barang (12 km) | |||
Delang-Puri (29 km) | |||
Jharsuguda-Rengali (26 km) | |||
Khurda Road-Barang 3rd line (35 km) | |||
Kirandul-Jadgalpur (150 km) | |||
Raipur-Titlagarh with Material Modifications (290 km) | |||
Rajatgarh-Barang (20 km) | |||
Sambalpur-Talcher (174 km) | |||
Sambalpur-Titlagarh (182 km) | |||
East Central Railway | |||
Chandrapura-Rajabera-Bhandaridah (11 km) | |||
Danea-Ranchi Road (25 km) | |||
Garhwa Road-Ramna (32 km) | |||
Hajipur-Ramdayalu Nagar (48 km) | |||
Jarangdih-Danea Patch Doubling (29 km) | |||
Katreah-Kursela Incl. bridge on River Kosi (7 km) | |||
Sonepur-Hajipur Including Gandak Bridge (6 Km) | |||
Eastern Railway | |||
Ambikakalna-Nabadwip Dham (23 km) | |||
Azimganj-Manigram (20 km) | |||
Bandel-Boinchi - 3rd line(31 km) | |||
Barharwa-Bonidanga (5 km) | |||
Bazar Sau-Azimganj Jn.(42 km) | |||
Bethuadhahari-Plassey (23 km) | |||
Boinchi-Shaktigarh 3rd line (26 km) | |||
Chandpara-Bongaon with Material Modifications (55 km) | |||
Chinpai-Sainthia with Material Modifications (122 Km) | |||
Dakshin Barasat-Lakshmikantapur with material modifications (72 km) | |||
Dankuni-Bhattanagar (4 km)Â | |||
Dankuni-Chandanpur- 4th Line with Material Modifications (38 Km) | |||
Ghutiari Sharif-Canning with Material Modifications (56 Km) | |||
Habra-Bongaon Phase-I (Habra-Chandpara) & Machlandapur-Swarup Nagar (37 Km) | |||
Kalinarayanpur-Krishnanagar with Material modifications (115 Km) | |||
Kalinarayanpur-Shantipur with Material modifications (24 Km) | |||
Katwa-Patuli with Material Modifications (70 km) | |||
Krishnanagar-Bethuadahari (28 km) | |||
Liluah-Dankuni 3rd Line with Extension to Furfura Sharif (30 Km) | |||
Magrahat-Diamond Harbour with Material modifications (66 Km)Â | |||
Monigram-Nimtita (34 km) | |||
Nabadwip Dham-Patuli (22 km) | |||
Nalhati-Sagardighi (26 km) | |||
New Alipur-Akra & Budge Budge-Pujali with Material Modification (41 Km) | |||
Pandabeswar-Chinpai (21.41 km) with Material Modification (52 Km) | |||
Pirpainti-Bhagalpur (59 km) | |||
Plassey-Jiaganj (54 km) | |||
Princepghat to Majherhat Doubling of Circular Railway (5 km) | |||
Sagardigi-Azimganj Cabin (16km) | |||
Sahibganj-Pirpainti (23 km) | |||
Sainthia-Tarapith 3rd line (22 km) | |||
Sealdah Div.- 2nd passenger Line bet. Mile 5 B and New Alipore (2 km) | |||
Sonarpur-Canning with Material Modification (53 Km) | |||
Sondalia-Champapukur with Material Modification (35 Km) | |||
Tala-Princep Ghat- DL of Circular Rly.(10 km) | |||
Tarapith-Rampurhat-provision of 3rd line(7 km) | |||
Tinpahar-Sahibganj (38 km) as PH-I of doubling of Tinpahar-Bhagalpur | |||
North Central Railway | |||
Bhimsen-Jhansi (206 Km) | |||
North Eastern Railway | |||
Aurnihar-Manduadih (39 Km) | |||
Chhapra-Ballia Patch Doubling (65 km) | |||
Northeast Frontier Railway | |||
Ambari Falakata-New Maynaguri (37 km) | |||
Lumding-Hojai Patch Doubling (45 km) | |||
New Bongaigaon-Kamakhya via Rangiya (142 km) | |||
New Coochbehar-Gumanihat (29 km) | |||
New Coochbehar-Samuktala Road (29 km) | |||
Northern Railway | |||
Ambala Cantt-Dhapper (Ph.I) (23 Km) | |||
Anand Vihar-Tilak Bridge 3rd & 4th line (10 km) | |||
Bhadoi-Janghai | |||
Chakki Bank-Bharoli (4 km) | |||
Dayabasti-Grade Separator (6 Km) | |||
Haridwar-Lakshar (27 km) | |||
Jallandhar Cantt-Suchi Pind - Doubling with Electrification (4 km) | |||
Jallandhar-Pathankot-Jammu Tawi (211 km) | |||
Kathua-Madhopur Doubling Across Bridge No.16, 18 & 19 (0.3 Km) | |||
Kathua-Madhopur Punjab-Doubling Across Ravi Bridge (1 Km) | |||
Lahota-Bhadoi (39 Km) | |||
Mansa-Bhatinda Ph.I with Material Modification (53 Km) | |||
Meerut-Muffarnagar (55 Km) | |||
Mrithal-Bhangala -Doubling Across Beas Bridge (1 Km) | |||
New Delhi-Tilak Bridge 5th and 6th line (3 km) | |||
Phapamau-Allahabad (13 Km) | |||
Raibareilly-Amethi (60 Km) | |||
Sambha -Vijaypur Jammu-Doubling Across Basanter Bridge (0.2 Km) | |||
Tughlakabad (Jn. Cabin)-Palwal 4th line (34 km) | |||
Utretia-Raibareilly (66 Km) | |||
Utretia-Zafrabad (224 Km) | |||
North Western Railway | |||
Abu Road-Sarotra Road Patch doubling (23 km) | |||
Ajmer-Bangurgram (48 km) | |||
Alwar-Bandikui (60 km) | |||
Bangurgram-Guria Patch DL (47 km) | |||
Bhagat ki Kothi-Luni (28 km) | |||
Guriya-Marwar (44 km) & Karjoda-Palanpur (5 km) | |||
Rani-Keshavganj (60 km) | |||
Rani-Marwar Jn Patch DL (55 km) | |||
Rewari-Manheru (69 km) | |||
Sarotra Road-Karjoda Patch Doubling (24 km) | |||
Swaroopganj-Abu Road Patch Doubling (25 km) | |||
South Central Railway | |||
Daund-Gulbarga Doubling (225 km) and Pune-Guntakal Electrification (641 km) | |||
Guntur-Tenali Doubling with Electrification (24 km) | |||
Kazipet-Vijaywada 3rd line with Electrification (220 km) | |||
Krishnapatnam-Venkatachalam Doubling with electrification (23 Km) | |||
Mancheryal-Peddampet Patch Tripling (4 Km) | |||
Mudkhed-Parbhani (81 Km) | |||
Raghavapuram-Mandamari Patch Tripling (24 Km) | |||
Vijaywada-Gudivada-Bhimavaram-Narsapur, Gudivada-Machlipatnam & Bhimavaram-Nidadavolu with Electrification (221 km) | |||
South East Central Railway | |||
Bilaspur-Urkura 3rd line (110 km) | |||
Champa-Jharsuguda 3rd Line(165 km) | |||
Durg-Rajnandgaon 3rd Line (31 Km) | |||
Kalumna-Nagpur (6 Km) | |||
Khodri-Annupur with flyover at Bilaspur (62 km) | |||
Salka Road-Khongsara Patch doubling (26 Km) | |||
South Eastern Railway | |||
Andul-Baltikuri (7 km) | |||
Champajharan-Bimlagarh (21 km) | |||
Dangoaposi- Rajkharswan 3rd Line (65 Km) | |||
Goelkera-Manoharpur 3rd Line (40 km) | |||
Kharagpur-Narayangarh 3rd Line (20 km) | |||
Manoharpur-Bondamanda 3rd Line(30 km) | |||
Panskura-Kharagpur 3rd Line with Material modification (78 Km) | |||
Rajkharswan-Chakradharpur 3rd Line (20 km) | |||
Rajkharswan-Sini-3rd line (15 Km) | |||
Sini-Adityapur (23 km) 3rd Line | |||
Tamluk Jn. Cabin-Basulya Sutahata (24 km) | |||
Tikiapara-Santragachi -IV Liine (6 km) | |||
Southern Railway | |||
Ambalapuzha-Haripad (18 km) | |||
Attipattu-Korukkupettai 3rd Line (18 km) | |||
Chengalpattu-Villupuram (103 km) with material modification (133 Km) | |||
Chenganur-Chingavanam (27 km) | |||
Chennai Beach-Attipattu 4th Line (22 km) | |||
Chennai Beach-Korukkupet 3rd Line (4 km) | |||
Chennai Central-Basin Br. Jn. -Provision of 5th & 6th Line (2 km) | |||
Ernakulam-Kumbalam Patch Doubling (8 km) | |||
Kankanadi-Panambur Patch Doubling (19 km) | |||
Kumbalam-Thuravur Patch Doubling (16 km) | |||
Kurruppanthara-Chingavanam (27 km) | |||
Mullanturutti-Kuruppantara (24 km) | |||
Omalur-Metturdam Patch Doubling with electrification (29 km) | |||
Thanjavur-Ponmalai DL (47 km) with a Byepass line before Ponmalai (1 km) | |||
Tiruvallur-Arakkonam 4th Line (27 km) | |||
Villupuram-Dindigul (with Electrification) (273 km) | |||
South Western Railway | |||
Bangalore-Whitefield-Bangalore City-Krishnarajapuram (23 km) Quadrupling | |||
Birur-Shivani -Patch Doubling (29 km) | |||
Hosadurga Road-Chikjajur - Patch doubling (29 km) | |||
Hospet-Hubli-Londa-Tinaighat-Vasco-de-Gama (352 km) | |||
Ramanagaram-Mysore(92 km) with Electrification of Kengeri-Mysore | |||
Shivani-Hosadurga Road (10 km) | |||
Toranagallu-Ranjithpura (23 km) | |||
Yeshwantpur-Yelahanka-doubling with Overhead equipment (12 km) | |||
West Central Railway | |||
Barkhera-Habibganj 3rd Line (41 km) | |||
Bhopal-Beena 3rd Line (143 km) | |||
Bina-Kota (283 km) | |||
Budhni-Barkhera - 3rd Line (33 km) | |||
Ghat Pindrai-Belkhera Patch DL (6 km) | |||
Guna-Ruthiyai (21 km) | |||
Itarsi-Bhudni 3rd line (25 km) | |||
Western Railway | |||
Palanpur-Samakhayali (275 km) | |||
Surat-Kosamba PH-I of 3rd Line Between Vadodara and Virar (35 Km) | |||
Udhna-Jalgaon with Electrification (307 Km) | |||
Vatva-Ahmedabad-3rd line with Automatic Signalling (8 km) | |||
Viramgam- Surendranagar (65 Km) | |||
Viramgam-Samakhiali (182 Km) |