Weighting Diagram of Cost of Construction of a Pucca Building in Urban Sector of Andhra Pradesh (2005-2006) | ||
Selected Item | Total Expenditure in Rs. | Weight |
Clay Bricks | ||
Sand -Fine | ||
Sand Medium | ||
Sand- Coarse | ||
Stone Ballast 20 mm | ||
Stone Ballast 40 mm | ||
Grainate Stone | ||
Ordinary Cement | ||
Teak | ||
Other Wood (Local) | ||
MS Round Bars 6 mm Guage | ||
MS Round Bars 8 mm Guage | ||
MS Round Bars 10 mm Guage | ||
MS Round Bars 12 mm Guage | ||
MS Round Bars 16 mm Guage | ||
Polished Stones | ||
Marble Stones | ||
S.W Pioes 100 mm Dia | ||
P.V.C Pipes 110 mm Dia | ||
Wall Paints | ||
Wires (Interior) | ||
Door Frames-Wood | ||
Material Total : | ||
Skilled - Mason | ||
Skilled - Carpenter | ||
Skilled- Electrician | ||
Skilled- Plumber | ||
Un- Skilled - Man | ||
Un- Skilled Woman | ||
Labour Total : | ||
Water Connection Charges | ||
Electricity Connection Charges | ||
Drainage Connection Charges | ||
Material Mixing Charges | ||
Supervisory Charges | ||
Engineering Charges | ||
Plan Approval Charges | ||
Rents Paid towards Construction Equipments | ||
Miscellaneous Total : | ||
Total Cost of Construction |